Thursday, August 11, 2011

Tracking the rail project in Wallingford

As published in the Record Journal, Monday August 8, 2011

By Mary Ellen Godin
Record-Journal staff
mgodin@record-journal.com
(203) 317-2255

WALLINGFORD — Travel speeds, downtown traffic, land acquisition and changes in the Judd Square area are some of the concerns being raised by the public over plans for commuter rail service from New Haven to Springfield, Mass.

Plans call for upgrading signals along the 62-mile stretch, which could begin as early as next spring. But locally, the public voiced concerns at a meeting last week over a proposal to move the train stop to Judd Square, with an elevated platform and parking for 200 cars.

The state Department of Transportation held the first of many informational sessions last Thursday with residents and town officials over where and how to lay out the new station. The rail line will increase commuter and inter-city service while also providing high-speed Acela transit along the corridor.

Springfield will become a central connector with service to Boston, Vermont and finally to Montreal. The project consists of double tracking 62 miles of track, upgrading the signals, building new stations in North Haven, Newington and Enfield, relocating Wallingford’s station and building new elevated platforms, walkways and parking garages in each town.

“Nothing has been set in stone,” said DOT Project Manager John Bernick.
He asked town officials to create a panel to act as an advisory board throughout the project.

Wallingford has the most crossings of any municipality along the corridor — 10, eight with signals and two unsignaled gates. The most heavily trafficked areas are Parker, Hall, Ward and Quinnipiac streets. The town now has five or six trains passing through per day. The rail project calls for 25.

Public officials have said they are concerned that more trains, which can go as fast as 110 mph, would pose a safety threat to residents and disrupt nearby businesses.

City Councilor Jerry Farrell opposed Amtrak’s taking any land from Most Holy Trinity Church. Bernick assured him that wouldn’t happen.

Farrell also he had concerns about 25 trains roaring through a very densely populated section of town every day. The crossings are at grade. He was assured that just because the trains had the potential to reach 110 mph didn’t mean they would travel that fast through Wallingford or other high density areas. “No matter where you place it or combine it, grade crossings are going to be a problem,” Bernick said.

A traffic study conducted by Wilbur Smith & Associates reviewed the traffic signals at Parker, Hall, Ward and Quinnipiac streets and gave several of them failing grades should the anticipated commuter and intercity service start with no changes in existing traffic routes. Solutions include some road widening in certain areas, signal changes and right-turn-only lanes.

Residents of Judd Square and the nearby area expressed concerns that their parking, already in short supply, would be impacted. Bernick said no parking would be taken away and Amtrak plans to use land now housing a warehouse for that purpose.

There were only rough schematics of the site, parking garage and walk-up from Route 5 because project leaders hope to gather more public input on the location of the new train platform and design specifications. Judd Square is not a definitive site — moving the stop several blocks to the north has also been discussed — but is the best for the project, Bernick said.

Councilor Craig Fishbein questioned the cost of the project and the amount Amtrak receives annually in subsidies to support its operation. He said that without an obvious demand by people working in other towns, he didn’t see how the operation could sustain itself. The cost of the project is set at $647 million, and a $110 million shortfall is expected for the Hartford-to-Springfield leg, which planners expect will come from the federal government.

“You would be better off giving the money to the people,” Fishbein said.

Bernick replied that demand has already been proven and the project will offer significant economic development opportunities to communities with train stations. He also said increased usage of Metro-North has made it the most profitable service in the U.S.

Other benefits are that the ability to travel to Boston and New York in one to two hours could make office space in Meriden or Wallingford more attractive. Shuttle buses to and from industrial parks are also a possibility and the station will connect with the public service bus lines.

The public meetings in the cities and towns along the rail line will become part of the environmental impact study expected this fall. Upgrades to the signals could begin as early as next spring, Bernick said.

Gail DeLucia, president of the Judd Square Homeowners Association, got on board with the project after she learned the residents would not lose any parking. She was careful to say she was speaking as an individual and not for the group. But the sluggish economy and job market offer more reasons to invite commerce and create jobs.

“We have to look to the future,” DeLucia said, “or we don’t get any solution.”

Tuesday, August 9, 2011

FROM WALLINGFORD - Truth overtakes rail project

V-Knight_S

This week’s FROM WALLINGFORD was written by Stephen Knight

As published in the Record Journal, Sunday August 7, 2011

I have been a student of the railroad industry for my entire adult life; as a student in graduate school, as a keenly interested observer, and as a professional transportation consultant. So I write this column with considerable angst, because it is my conclusion that the proposed New Haven-Hartford-Springfield commuter rail project that will run through Wallingford is a boondoggle of fantastic proportions. My inherent predisposition to support this project is overwhelmed when confronted with the 1) downright mythical speed and service projections, 2) wildly optimistic ridership projections and 3) blindly underestimated capital and operating expenses.

Speed and service projections: In a May 9 press release, Gov. Malloy stated that these trains would reach “speeds up to 110 miles per hour.” I say: only if you catapult the trains from every station like they do jet fighters off an aircraft carrier. Why? First of all, there will eventually be 11 stops in the 62 miles between New Haven and Springfield. That’s an average of less than six miles between stops. So where exactly will these trains do 110 mph? And — are you ready for this? — the service will commence with hand-me-down equipment from Shoreline East. According to their latest schedule, those trains, making all the stops, move between New Haven and New London averaging less than 50 mph, and do so on the most advanced, best maintained railroad track in America. Secondly, this speed in a corridor with thirty-eight grade crossings? Really? So calling the NHHS project high speed rail is utterly fictitious.

Ridership projections built on the sentiment “Build it and they will come”: in calculating potential ridership, the numbers presented assume a) many more daily Amtrak trains running on the line; b) enormous numbers of passengers feeding the line from the so-called “Knowledge Corridor” line in central Massachusetts which has yet to be rebuilt; and c) thousands upon thousands of people willing to live in this corridor and work 2 ½ hours away in New York City. In other words, the number of commuters between New Haven and Springfield that is supposedly the driving force behind this project could never, ever justify the price tag, so numbers assuming a complete northeastern United States rail system build out are used to puff up the stats.

Capital and operating expenses: The price tag for rail line and station construction alone is $647 million, and the project is counting on huge support from the feds. Here is the latest fed response: State of Connecticut request — $227 million. Fed grant: $30 million. Result: the project has already contracted to providing trains only during peak commuter times. And how much money is allocated to purchase rolling stock — the stuff you ride on? Zero. As mentioned above, the plan is to use the existing Shore Line East equipment until, well, who knows?

As for operating expenses, somehow the project is making revenue estimates, but they haven’t even set the fare schedule. How do you do that? But even assuming (do you see that word a lot here?) their revenue and ridership projections are accurate, there is an inherent, unavoidable, inevitable huge annual cash subsidy. This is not unusual. This is the norm, but could someone in Hartford admit that?

So here’s the rub. Even more than I love railroads, I love the truth. The unvarnished, straight up, tell-it-like-it-is, we can take it truth. And we aren’t getting it. We are being fed pretty pictures, fantastic blue-sky fuzzy numbers and gauzy descriptions of an idyllic life in a future northeastern U.S. economy that seems farther from reality every single day.

If these words seem harsh, they spring from disappointment.

Disappointment that this project is not a practical, financially sensible fit for the market in which it is to operate, and disappointed that you and I are, yet again, being treated like proverbial mushrooms: kept in the dark and covered with . . . well, you know what I’m saying.